Venture Global’s Plaquemines LNG to introduce hazardous fluids to first block

US LNG exporter Venture Global LNG has received approval from the FERC to introduce hazardous fluids to the first liquefaction block at its Plaquemines LNG export plant in Louisiana.

The regulator said on Thursday it had granted Venture Global Plaquemines LNG to commission and introduce hazardous fluids to the liquefaction train system block 1.

This approval is based on FERC staff review of the information filed on November 12 and November 19, 2024, it said.

The FERC noted that approval of other interconnecting systems is required prior to introducing hazardous fluids to LTS block 1.

Venture Global’s newbuild carrier, Venture Bayou, recently arrived at the Plaquemines LNG export plant as the facility nears the launch of its first LNG production.

The 174,000-cbm LNG carrier was on Friday still located at the LNG plant along the Mississippi River, according to its AIS data provided by VesselsValue.

Prior to this vessel, the Plaquemines LNG facility received a cool-down cargo in August onboard the 2020-built 174,000-cbm, Qogir.

In August, Venture Global secured approval to commission the liquefaction train system block 1 with nitrogen.

The FERC granted the commissioning of the liquefaction train system block 4 with nitrogen last month, block 3 on September 30, and block 2 on September 10.

Most recently, Venture Global won approval to commission block 5 with nitrogen.

20 mtpa

Venture Global took a final investment decision in May 2022 on the first phase of the Plaquemines project with a capacity of 13.3 mtpa and the related pipeline. It also secured $13.2 billion in project financing.

In March last year, the company sanctioned the second phase of the Plaquemines LNG export plant in Louisiana and also secured $7.8 billion in project financing.

The full project, including the second stage, will have a capacity of 20 mtpa coming from 36 modular units, configured in 18 blocks.

Each train has a capacity of 0.626 mtpa.

Venture Global previously said it expects to start LNG production this year, while commissioning of the facility is expected to last about two years.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.
spot_img

More News Like This

Venture Global shipped 127 LNG cargoes in Q2

US LNG exporter Venture Global shipped 127 LNG cargoes from its Calcasieu Pass and Plaquemines LNG export terminals in the second quarter of this year.

Venture Global’s shipping unit inks $1.5 billion vessel loan facility

Venture Global's unit Venture Global Shipping Holdings entered into a senior secured term loan facility of up to $1.5 billion.

EnBW buys more LNG from Venture Global

German energy firm EnBW has agreed to buy more liquefied natural gas from US LNG exporter Venture Global LNG.

Venture Global seeks FERC OK for CP2 LNG expansion

US LNG exporter Venture Global LNG has filed a new application with the US FERC seeking approval to add approximately 11.7 million metric tonnes per annum of capacity at its CP2 LNG project in Louisiana.