Cheniere to introduce fuel gas to second Corpus Christi LNG expansion train

US LNG exporter Cheniere is nearing the introduction of fuel gas to the second train of the Corpus Christi Stage 3 expansion project in Texas as part of the commissioning phase.

According to a filing with the US FERC dated May 6, Cheniere’s unit Corpus Christi Liquefaction (CCL) sent compliance statements and associated documentation to the regulator.

“The compliance statements and associated documentation are in support of a forthcoming request by CCL to introduce fuel gas to midscale Train 2,” it said.

A separate filing shows that CCL also submitted the same documents in support of a forthcoming request to introduce hot oil to the train.

Cheniere made the final investment decision on the CCL Stage 3 expansion project, worth about $8 billion, in June 2022.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa, adding to the three operational trains, each with a capacity of about 5 mtpa.

In March, Cheniere’s EPC partner, Bechtel, turned over care, custody, and control of CCL Stage 3 Train 1 and associated systems to Cheniere ahead of schedule.

Cheniere said in its financial report in February that about 20 percent of Train 2 systems “turned over to commissioning and start-up teams who are beginning to place those systems into service.”

CEO Jack Fusco said that the company continues to target the first three trains to ramp up production by the end of this year and all seven trains to be substantially complete by the end of 2026.

The project was 82.5 percent complete as of the end of March this year.

Upon substantial completion of all seven trains of CCL Stage 3 in 2026, the expected total production capacity of the Corpus Christi liquefaction facility will be over 25 mtpa of LNG.

Further expansion

In addition to this expansion, Cheniere received approval from FERC in March to build two more midscale trains at its Corpus Christi LNG plant.

Cheniere recently sought and won approval from FERC to start site preparation activities for the trains.

The proposed midscale trains 8 and 9 project or project includes adding two midscale
liquefaction trains, each with an expected liquefaction capacity of about 1.49 mtpa, and associated facilities, as well as increasing the authorized loading rate at the terminal’s existing marine berth.

In February, Fusco confirmed that the company still expects to make FID to build two more midscale trains at its Corpus Christi LNG plant this year.

Most Popular

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

Cheniere adds new board member

US LNG exporting giant Cheniere has appointed Britt Vitalone to serve as a member of its board of directors.

Baker Hughes scores equipment and services contracts for Cheniere’s Sabine Pass LNG terminal

US energy services firm Baker Hughes said it had secured three "substantial" awards for Cheniere’s Sabine Pass LNG export facility in Cameron Parish, Louisiana.

Argent LNG awards marine and site engineering services contract to GIS

Argent LNG has awarded a marine, environmental, and site engineering services contract to Louisiana-based GIS Engineering in support of the federal permitting process for its proposed 25 mtpa LNG export terminal at Port Fourchon.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.