Cheniere kicks off commissioning at fifth Corpus Christi expansion train

US LNG exporter Cheniere has started commissioning activities at the fifth train of the Corpus Christi Stage 3 expansion project in Texas.

“As part of initial commissioning of Midscale liquefaction Train 5, Cheniere and EPC contractor Bechtel will begin startup/commissioning operations,” according to a report filed by Corpus Christi Liquefaction with the Texas Commission on Environmental Quality.

“Cheniere and EPC contractor will be utilizing good engineering practices during startup/commissioning activities. The thermal oxidizer, furnace, and ground flares will be maintained and operated during the startup/commissioning activities to ensure hydrocarbons are properly combusted,” the firm said.

In addition, CCL also received approval from the US FERC on Wednesday to introduce propane into the midscale Train 5 thermal oxidizer and hot oil furnace for the Stage 3 project.

Over 30 mtpa

Last month, Cheniere achieved substantial completion of the fourth liquefaction train at the Corpus Christi Stage 3 expansion project.

This followed the substantial completion of the first liquefaction train in March last year, ahead of schedule, and the company’s completion of the second liquefaction train in August and the third train in October.

“Our seven-train, 10+ million-tonne-per-annum (mtpa) project continues to track ahead of schedule and on budget, and we expect the remaining three trains to achieve substantial completion in 2026,” Cheniere said last month.

Cheniere made the final investment decision on the Corpus Christi Stage 3 expansion project, worth about $8 billion, in June 2022, while Bechtel officially started construction on the project in October of the same year.

The Stage 3 expansion project was 93 percent complete as of the end of November.

Moreover, Cheniere made a positive final investment decision to build two more midscale trains at its Corpus Christi LNG plant in June last year.

The CCL midscale trains 8 and 9 project is being built adjacent to the Corpus Christi Stage 3 project and consists of two midscale trains with an expected total liquefaction capacity of over 3 mtpa of LNG and other debottlenecking infrastructure.

Upon completion of the project, and together with expected debottlenecking and CCL Stage 3, the Corpus Christi LNG terminal will reach over 30 mtpa in total liquefaction capacity later this decade.

In addition to this expansion, Cheniere received approval from the US FERC to initiate the environmental pre-filing review for its Corpus Christi Liquefaction Stage 4 project.

The trains will have a peak production capacity of approximately 24 mtpa of LNG.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.
spot_img

More News Like This

Cheniere adds new board member

US LNG exporting giant Cheniere has appointed Britt Vitalone to serve as a member of its board of directors.

Baker Hughes scores equipment and services contracts for Cheniere’s Sabine Pass LNG terminal

US energy services firm Baker Hughes said it had secured three "substantial" awards for Cheniere’s Sabine Pass LNG export facility in Cameron Parish, Louisiana.

Argent LNG awards marine and site engineering services contract to GIS

Argent LNG has awarded a marine, environmental, and site engineering services contract to Louisiana-based GIS Engineering in support of the federal permitting process for its proposed 25 mtpa LNG export terminal at Port Fourchon.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.