Jera seeks OK to start pre-filing process for Hawaii LNG project

Japan's power firm and LNG trader Jera is seeking approval from the US FERC to initiate the pre-filing process for its planned FSRU-based LNG import facility in Hawaii.

Longboard TerminalCo, a wholly-owned subsidiary of Jera Americas, submitted a request on May 15 to initiate the Commission’s pre-filing review process for the proposed LNG import terminal and related natural gas facilities to be located in state waters offshore Kalaeloa (Barbers Point), and onshore within Campbell Industrial Park, on Oahu, Hawaii.

Jera’s unit said the purpose of the project is to provide a near-term supply of natural gas to support Oʻahu’s energy transition goals, including affordability, reliability, and emissions reduction.

FSRU and subsea pipeline

The company noted that LNG will be imported as an alternative to fuel oil using a disconnectable, non-jurisdictional floating storage and regasification unit (FSRU), with an expected storage capacity of 138,000 cbm to 174,000 cbm.

Moreover, the LNG supplies will be delivered by ship-to-ship transfer to the FSRU, where it will be regasified and sent onshore via a single point mooring (SPM) system and 3-mile-long, 16-inch diameter subsea natural gas pipeline-

Jera noted that the jurisdictional project facilities will include the SPM system, the subsea natural gas pipeline, an approximately 2-acre onshore receiving facility (ORF) connecting the subsea pipeline to onshore pipelines, and other appurtenant and ancillary facilities necessary for the safe and reliable operation of the project.

These facilities will provide a “dependable” fuel source for firm power generation on Oahu, it said.

In October last year, Jera’s unit signed a strategic partnering agreement with the government of Hawaii to support the US island state’s plans to shift away from oil by using alternative fuels, including natural gas.

In March this year, the company submitted a proposal to the government of Hawaii to build LNG infrastructure and a 500 MW hybrid combined-cycle and simple-cycle gas turbine facility on Oahu, valued at $2 billion.

FSRU charter

According to the FERC submittal, Longboard LNG intends to enter into a long-term time charter party (TCP) agreement with an “experienced FSRU owner and operator” to provide offshore regasification services for the project.

The FSRU owner will be responsible for vessel design, classification, certification, and operation, with oversight from Longboard LNG.

Jera noted that the NGA Section 3 application for the project will not be based on a specific vessel.

Instead, Longboard LNG will define a “conservative design envelope of environmental and safety parameters consistent with the size and class of modern FSRUs expected to serve the project.”

The specific vessel will be confirmed once the TCP is awarded, and the FSRU owner may periodically substitute vessels within its fleet for maintenance or operational reasons, it said.

Longboard LNG anticipates that annual LNG demand from power generation, industrial facilities, retail gas customers, and LNG bunkering will peak at approximately one million metric tons per annum (mtpa), equivalent to roughly one LNG carrier arrival every three to four weeks, depending on vessel size.

The company estimates that the project will provide approximately 0.6 mtpa of LNG for power generation and gas distribution, and approximately 0.4 mtpa of LNG for marine fuel bunkering operations.

2030

Longboard LNG anticipates filing its formal application with the Commission by December 2026, and anticipates requesting that the Commission issue an order authorizing the LNG project no later than the second quarter of 2028.

Moreover, Longboard LNG anticipates filing the initial project implementation plan and requesting authorization to commence construction soon after receipt of the Commission’s order authorizing the project.

The firm anticipates FERC authorizing the project in the second quarter of 2028, and an authorization to proceed and commence project construction in the third quarter of 2028.

According to the schedule, the project is expected to go online in the first quarter of 2030.

Most Popular

LNG Canada offers option to First Nations to invest in Phase 2 storage tank

Shell-led LNG Canada has signed an agreement with five northwestern B.C. First Nations, giving them the option to invest up to C$1 billion ($711 million) to acquire an LNG storage tank slated for construction as part of the expansion of its Kitimat LNG export facility on the west coast of Canada.

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

Argent LNG awards marine and site engineering services contract to GIS

Argent LNG has awarded a marine, environmental, and site engineering services contract to Louisiana-based GIS Engineering in support of the federal permitting process for its proposed 25 mtpa LNG export terminal at Port Fourchon.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Cheniere’s Corpus Christi Stage 3 project 98 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 98 percent complete, as it continues to progress ahead of schedule, according to the latest construction update.

Japan’s Jera forms LNG unit

Japan's power firm and LNG trader Jera has established Jera Global Energy Solutions (Jera GES) to develop and manage its long-term LNG, upstream, lower-carbon fuels, and shipping portfolio.