Cheniere, Bechtel seal EPC deal for first Sabine Pass LNG expansion phase

A unit of Cheniere Energy Partners has entered into a lump sum, turnkey, engineering, procurement, and construction (EPC) contract with Bechtel for the first phase of the Sabine Pass LNG expansion project in Louisiana. In addition, Bechtel has received a limited notice to proceed to start early engineering and procurement for the project.

Cheniere Energy Partners, a limited partnership formed by US LNG exporter Cheniere and the operator of the Sabine Pass LNG terminal, announced the award by its unit Sabine Pass Liquefaction Stage V in a statement on Thursday.

The company did not provide the pricing details in the statement.

However, Cheniere Partners said in a SEC filing later on Thursday that the EPC contract is valued at $4.69 billion.

Cheniere’s Sabine Pass facility currently has a capacity of approximately 30 million tonnes per annum (mtpa) following the launch of the sixth train in February 2022.

The expansion project is being developed for up to three large-scale liquefaction trains with an expected total peak production capacity of up to approximately 20 mtpa of LNG, inclusive of estimated debottlenecking opportunities and supporting infrastructure.

Cheniere Partners is developing the project in phases.

The EPC agreement with Bechtel for Phase 1 includes a single train, Train 7, a boil-off gas reliquefaction unit, along with supporting infrastructure and tie-ins to the existing Sabine Pass LNG terminal.

Inclusive of estimated debottlenecking, Phase 1 has an expected total LNG production capacity of over 6 mtpa.

Cheneire Partners said Phase 1 is commercially underpinned by long-term agreements with “creditworthy counterparties”, and a positive final investment decision (FID) on Phase 1 is subject to, among other things, receipt of necessary regulatory approvals and an acceptable financing arrangement.

The Federal Energy Regulatory Commission (FERC) application for authorization to site, construct, and operate the expansion Project, as well as the Department of Energy (DOE) application authorizing the export of LNG to non-free trade agreement (non-FTA) countries, remain pending.

Last month, FERC released a draft environmental impact statement for Cheniere’s planned Sabine Pass Stage 5 expansion project.

The regulator concluded that construction and operation of the LNG project would result in “some adverse environmental effects; however, effects would be reduced to less-than-significant levels.”

Cheniere Partners expects to reach FID on Phase 1 by early 2027.

(Article updated to say that the value of the EPC contract is $4.69 billion.)

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.

LNG Canada offers option to First Nations to invest in Phase 2 storage tank

Shell-led LNG Canada has signed an agreement with five northwestern B.C. First Nations, giving them the option to invest up to C$1 billion ($711 million) to acquire an LNG storage tank slated for construction as part of the expansion of its Kitimat LNG export facility on the west coast of Canada.

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

Cheniere adds new board member

US LNG exporting giant Cheniere has appointed Britt Vitalone to serve as a member of its board of directors.

Baker Hughes scores equipment and services contracts for Cheniere’s Sabine Pass LNG terminal

US energy services firm Baker Hughes said it had secured three "substantial" awards for Cheniere’s Sabine Pass LNG export facility in Cameron Parish, Louisiana.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Cheniere’s Corpus Christi Stage 3 project 98 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 98 percent complete, as it continues to progress ahead of schedule, according to the latest construction update.