Gasunie’s Eemshaven LNG hub to resume gas supplies to Dutch grid on February 6

Dutch natural gas firm Gasunie is now planning to resume sendout to the grid from its LNG import hub in the port of Eemshaven on February 6.

A Gasunie spokeswoman told LNG Prime last week that the work on the heat connection would take longer than expected and the firm planned to resume sendout to the grid by the end of this week.

Gasunie previously said it would not be able to send natural gas from the terminal to the grid during January 13-30 due to an outage at RWE.

RWE operates a power plant in the port of Eemshaven which supplies heat to the terminal.

“We have been informed by RWE that additional time is needed to carry out the technical work for the connection of the heat pipeline,” the spokeswoman said in emailed comment on Wednesday.

“This changes the planning. We now expect to start up this Friday, February 3, after which the first gas can be sent out again on Monday, February 6,” the spokeswoman said.

Full capacity on March 1

Gasunie expects to reach full operations at the LNG hub on March 1.

However, both of these schedules depend on the completion of the work, the spokeswoman noted.

The facility operated by Gasunie’s EemsEnergyTerminal features two chartered FSRUs and they include the 26,000-cbm barge-based FSRU Eemshaven LNG and the 170,000-cbm Energos Igloo.

The heat connection is needed as sea water is too cold during this time of the year to be used for the regasification process.

Gasunie’s new terminal with a capacity of about 8 bcm per year started delivering regasified LNG to the Dutch grid in September and has up to date received eleven cargoes.

Shell previously booked 4 bcm while Czech utility CEZ took 3 bcm of the Eemshaven terminal’s total capacity. France’s Engie secured the remaining 1 bcm of capacity.

Most Popular

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

Eemshaven LNG capacity nearly booked up to 2036

Firms have booked the majority of the regasification capacities at the FSRU-based LNG import facility in the Dutch port of Eemshaven, owned by Gasunie and Vopak, for the period 2028-2036, as part of the planned extension of the terminal's operations beyond 2027.

Nord Gas Solutions bags contract for Exmar FSRU conversion

Nord Gas Solutions, previously known as Wartsila Gas Solutions, has secured a contract from Belgium-based shipping firm Exmar to supply a regasification system for the latter's FSRU conversion which will be installed in the Dutch port of Eemshaven.

Gasunie and Vopak take conditional investment decision on Eemshaven LNG extension

Dutch partners Gasunie and Vopak have taken a conditional investment decision to extend operations of their FSRU-based LNG import facility in the Dutch port of Eemshaven beyond 2027.

Dutch LNG terminals assess demand for ammonia imports

Dutch Gate and Eemshaven LNG terminals, both operated by Gasunie and Vopak, are assessing market demand for renewable and low-carbon gas, including imports of ammonia.