Germany’s Hanseatic testing market interest in Stade LNG terminal

Hanseatic Energy Hub has launched a non-binding phase of an open season to test market interest in its Stade LNG import terminal in the northern German town.

According to the Stade LNG terminal developer, the non-binding phase will run until February 1, 2021.

Urban Stojan, partner and project manager, said the launch “marks an important step towards securing binding contracts and making the terminal a reality.”

To remind, global market players have already shown interest in the German LNG facility. As a result, Hanseatic signed in September LOIs with nine players interested in taking capacity at the terminal.

Located on the Elbe river within the Dow industrial park, the terminal will have a 12 Bcm/year capacity. This will make it the largest of the three planned LNG terminals in northern Germany.

“We have been working closely with the market to prepare our open season and are keen to engage with all parties interested in capacity in our terminal,” Hanseatic commercial and regulatory director Danielle Stoves said.

“During the non-binding phase, we will seek feedback on the proposed commercial offering which will allow us to ensure the binding phase of the open season meets the requirement of potential customers,” Stoves said.

Launch in 2026

The terminal will have two jetties and the prime jetty will be capable of receiving ships up to Q-Max size.

Additionally, the facility will also feature a dedicated jetty for small-scale ships.

This would allow Hanseatic customers to take advantage of LNG bunkering because of the proximity to the Hamburg port.

Furthermore, the terminal will also feature LNG truck loading and rail loading facilities.

According to its website, Hanseatic consists of LNG infrastructure, energy, port specialists, and external experts.

These include Dow, Niedersachsen Ports, Lotsenbrüderschaft, Fichtner, Müller-BBM Projektmanagement, and ARSU. Spain’s Reganosa Servicios is the owner’s engineer.

The partners plan to start construction in 2022 and launch the facility in 2026.

Most Popular

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

DET plans to launch Stade FSRU terminal in September

State-owned German LNG terminal operator DET plans to launch its Stade FSRU-based terminal in September this year.

DET says Stade FSRU terminal will not go into operation before Q2 2026

State-owned German LNG terminal operator DET expects that the Stade FSRU-based terminal will not go into operation before the second quarter of 2026 after it took over the construction of the superstructure from Hanseatic Energy Hub.

Stade FSRU arrives in Jordan

The 174,000-cbm FSRU Energos Force has arrived in the Jordanian port of Aqaba, according to Egypt's Ministry of Petroleum and Mineral Resources. State-owned German LNG terminal operator DET sub-chartered this 2021-built FSRU for deployment in Jordan, as it works on the next steps for the delayed Stade LNG import facility in Germany.

DET says Stade FSRU to be deployed in Jordan

State-owned German LNG terminal operator DET has sub-chartered the 2021-built 174,000-cbm FSRU, Energos Force, for deployment in Jordan, as it works on the next steps for the delayed Stade LNG import facility in Germany.