Cheniere kicks off commissioning at fourth Corpus Christi expansion train

US LNG exporter Cheniere has started commissioning activities at the fourth train of the Corpus Christi Stage 3 expansion project in Texas.

“As part of initial commissioning of midscale liquefaction Train 4, Cheniere and EPC contractor Bechtel will begin startup/commissioning operations,” according to a report filed by Corpus Christi Liquefaction with the Texas Commission on Environmental Quality.

“Cheniere will be utilizing good engineering practices during the startup/commissioning activities. The thermal oxidizer, furnace, and ground flares will be maintained and operated during startup/commissioning activities to ensure hydrocarbons are properly combusted, ” the company said.

Separately, CCL also received approval from the US FERC on Wednesday to introduce propane into the midscale Train 4 thermal oxidizer and hot oil furnace for the Stage 3 project.

Seven trains

Cheniere’s Corpus Christi plant currently liquefies natural gas at three operational trains, each with a capacity of about 5 mtpa.

In June 2022, Cheniere made the final investment decision on the Corpus Christi Stage 3 expansion project, worth about $8 billion, while compatriot Bechtel officially started construction on the project in October of the same year.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

In March 2025, Cheniere achieved substantial completion of the first liquefaction train at the Corpus Christi Stage 3 expansion project, while the company completed the second liquefaction train in August.

Cheniere is also nearing the completion of the third train.

Last week, FERC granted CCL’s request to introduce feed gas and refrigerants to the cold end of the midscale Train 3 – string 1, and hydrocarbons to the train 3 condensate system.

Cheniere said in its second-quarter results that it still expects substantial completion of Train 3 and first LNG from Train 4 before the year-end of 2025.

The Stage 3 expansion project was 87.9 percent complete as of the end of July.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.
spot_img

More News Like This

Cheniere adds new board member

US LNG exporting giant Cheniere has appointed Britt Vitalone to serve as a member of its board of directors.

Baker Hughes scores equipment and services contracts for Cheniere’s Sabine Pass LNG terminal

US energy services firm Baker Hughes said it had secured three "substantial" awards for Cheniere’s Sabine Pass LNG export facility in Cameron Parish, Louisiana.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Cheniere’s Corpus Christi Stage 3 project 98 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 98 percent complete, as it continues to progress ahead of schedule, according to the latest construction update.