Cheniere nears launch of sixth Sabine Pass train

US LNG exporter Cheniere is getting closer to the launch of the sixth production train at its Sabine Pass plant in Louisiana.

The Federal Energy Regulatory Commission (FERC) said in a letter dated June 29 it had approved Cheniere’s request to introduce gas and commission the Train 6 fuel gas system.

Cheniere’s chief executive Jack Fusco said in May the firm had still expected to commission the sixth unit at Sabine Pass by the end of 2021.

Moreover, the company expects substantial completion of the unit in the first half of 2022.

The 25 mtpa Sabine Pass plant has five operational trains and is currently the largest such facility in the US.

Bechtel is building the sixth train which will add 5 mtpa of capacity to the facility.

In total, this is the ninth train the engineering giant is building for Cheniere, including the Corpus Christi plant where Bechtel handed over the third train earlier this year.

Most Popular

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

Cheniere adds new board member

US LNG exporting giant Cheniere has appointed Britt Vitalone to serve as a member of its board of directors.

Baker Hughes scores equipment and services contracts for Cheniere’s Sabine Pass LNG terminal

US energy services firm Baker Hughes said it had secured three "substantial" awards for Cheniere’s Sabine Pass LNG export facility in Cameron Parish, Louisiana.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Cheniere’s Corpus Christi Stage 3 project 98 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 98 percent complete, as it continues to progress ahead of schedule, according to the latest construction update.