Cheniere’s Corpus Christi expansion project almost 84 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is almost 84 percent complete.

Cheniere’s Corpus Christi plant currently liquefies natural gas at three operational trains, each with a capacity of about 5 mtpa.

In June 2022, Cheniere made the final investment decision on the Corpus Christi Stage 3 expansion project, worth about $8 billion, while compatriot Bechtel officially started construction on the project in October of the same year.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

In March 2025, Cheniere achieved substantial completion of the first liquefaction train at the Corpus Christi Stage 3 expansion project, while the company is nearing the introduction of feed gas to the second train.

Cheniere’s unit, Corpus Christi Liquefaction, said in the April construction report filed with the US FERC on Wednesday that the overall project completion rate for Stage 3 is 83.8 percent.

The project was 82.5 percent complete at the end of March this year.

Stage 3 engineering and procurement were 98.5 percent and 99.8 percent complete as of the end of April 2025, respectively, while subcontract and direct hire construction work were 90.1 percent and 57.3 percent complete, respectively.

During April, key work fronts included aboveground piping in Train 2 – 6 and outside boundary limits (OSBL), concrete pours in Trains 2 – 7, structural steel erection in Trains 2 – 7 and OSBL, underground piping installation in Trains 5 – 7 and OSBL, and equipment setting in Trains 2 – 7.

CCL said additional continued work includes road improvements, drainage work, and mobilization of temporary facilities, equipment, and personnel.

During April, Bechtel will continue concrete foundations and pedestal works and other works in Trains 2-5, while it will continue excavation to support the upcoming concrete pours in Trains 6-7.

Cheniere’s Corpus Christi expansion project almost 84 percent complete1
Train 3 cryogenic rack (Image: Cheniere)

Further expansion

Upon substantial completion of all seven trains of CCL Stage 3 in 2026, the expected total production capacity of the Corpus Christi liquefaction facility will be over 25 mtpa of LNG.

In addition to this expansion, Cheniere received approval from FERC to build two more midscale trains at its Corpus Christi LNG plant.

Cheniere is also seeking approval from FERC to start site preparation activities for the trains.

The proposed midscale trains 8 and 9 project or project includes adding two midscale
liquefaction trains, each with an expected liquefaction capacity of about 1.49 mtpa, and associated facilities, as well as increasing the authorized loading rate at the terminal’s existing marine berth.

In February, Cheniere CEO Jack Fusco confirmed that the company still expects to make a final investment decision to build two more midscale trains at its Corpus Christi LNG plant this year.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

Cheniere adds new board member

US LNG exporting giant Cheniere has appointed Britt Vitalone to serve as a member of its board of directors.

Baker Hughes scores equipment and services contracts for Cheniere’s Sabine Pass LNG terminal

US energy services firm Baker Hughes said it had secured three "substantial" awards for Cheniere’s Sabine Pass LNG export facility in Cameron Parish, Louisiana.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Cheniere’s Corpus Christi Stage 3 project 98 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 98 percent complete, as it continues to progress ahead of schedule, according to the latest construction update.