Delfin seeks more time to build its US floating LNG export project

Delfin LNG, a unit of Delfin Midstream and the developer of a floating LNG export project in the Gulf of Mexico, has requested more time from US FERC to put into service the project’s onshore facilities in Louisiana.

The firm revealed this in a letter to US FERC seeking an additional one-year extension to construct, operate and maintain certain onshore metering, compression, and piping facilities until September 2023.

The facilities would transport and deliver natural gas to Delfin’s deepwater port in federal waters offshore Louisiana.

Delfin plans to install up to four self-propelled FLNG vessels that could produce up to 13 mtpa of LNG or 1.7 billion cubic feet per day of natural gas.

This is the fourth time Delfin has asked FERC for an extension to build the facilities.

However, this request follows a $3 billion long-term deal to supply liquefied natural gas to a unit of energy trader Vitol.

Under the SPA, Delfin will supply 0.5 million tonnes per annum on a free on-board (FOB) basis at its deepwater port to Vitol for a 15-year period.

In addition to the SPA, Vitol has completed a strategic investment in the company.

Delfin seeks more time to build its US floating LNG export project
Image: Delfin LNG

Besides the Vitol deal, Delfin has entered into term sheets or heads of agreement with other LNG off-takers.

The firm told FERC it expects to finalize these deals “soon”.

In addition to this commercial progress, Delfin has completed FEED with Samsung Heavy Industries and Black & Veatch for the construction of the units. The firm has recently
conducted meetings with MARAD, and the US Coast Guard, concerning compliance with the
conditions of its deepwater port authorization as well.

As a modular project consisting of four separate floating LNG vessels, Delfin requires only 2 to 2.5 mtpa of long-term off-take contracts to support a final investment decision and begin construction of its project.

“Given all this significant progress, Delfin LNG is on schedule to make FID on its first FLNGV by the end of this year,” it said.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.
spot_img

More News Like This

GTT bags Delfin FLNG gig

French LNG containment specialist GTT has secured a tank design order from South Korean shipbuilder Samsung Heavy for Delfin Midstream's 4.4 mtpa FLNG unit, which will be installed offshore Louisiana.

Argent LNG awards marine and site engineering services contract to GIS

Argent LNG has awarded a marine, environmental, and site engineering services contract to Louisiana-based GIS Engineering in support of the federal permitting process for its proposed 25 mtpa LNG export terminal at Port Fourchon.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Cheniere’s Corpus Christi Stage 3 project 98 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 98 percent complete, as it continues to progress ahead of schedule, according to the latest construction update.