NextDecade: US court revises FERC’s order for Rio Grande LNG

US LNG firm NextDecade said that the US Court of Appeals for the District of Columbia had revised its August 2024 judgment against the Federal Energy Regulatory Commission’s order for the first five liquefaction trains at the Rio Grande LNG facility in Texas.

In August 2024, the US Court of Appeals for the D.C. Circuit issued the order vacating FERC’s remand authorization of NextDecade’s Rio Grande LNG facility and the pipeline saying that the FERC should have issued a supplemental EIS during its remand process.

After that, FERC announced in September 2024 that it will prepare a supplemental environmental impact statement for NextDecade’s Rio Grande LNG project.

“We are pleased with today’s revised Court judgment, which ensures construction at the Rio Grande LNG facility will not be impacted by the Court,” said Matt Schatzman, NextDecade’s chairman and CEO.

“This is an excellent outcome for NextDecade’s shareholders, our partners in the project, the local community, and our customers. We look forward to continuing our work with FERC through the reauthorization process for our project,” he said.

NextDecade is currently building three trains at the site located on the north shore of the Brownsville Ship Channel in south Texas.

In July 2023, NextDecade took the final investment decision on the first three Rio Grande trains and completed a $18.4 billion project financing.

NextDecade awarded the $12 billion EPC contract to Bechtel, and it officially kicked off work on the plant in October 2023.

The company recently said it is also making “excellent” progress on commercializing Rio Grande LNG trains 4 and 5.

In addition, NwxtDecade announced plans to build up to five more trains at the Rio Grande LNG facility.

NextDecade said it is developing and beginning the permitting process for trains 6 through 8, which are wholly owned by NextDecade and are cumulatively expected to increase the company’s total liquefaction capacity by approximately 18 million tonnes per annum once constructed and placed into operation.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.
spot_img

More News Like This

Argent LNG awards marine and site engineering services contract to GIS

Argent LNG has awarded a marine, environmental, and site engineering services contract to Louisiana-based GIS Engineering in support of the federal permitting process for its proposed 25 mtpa LNG export terminal at Port Fourchon.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Adnoc’s XRG boosts stake in NextDecade’s Rio Grande LNG

Adnoc's investment unit XRG has completed the previously announced acquisition of an additional equity interest in Trains 4 and 5 of NextDecade's Rio Grande LNG terminal in Texas.

Cheniere’s Corpus Christi Stage 3 project 98 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 98 percent complete, as it continues to progress ahead of schedule, according to the latest construction update.