NextDecade’s Rio Grande LNG secures FERC extension

NextDecade's Rio Grande LNG has secured a three-year extension from the US FERC to complete construction and place into service five trains at its LNG export plant in Texas.

In 2019, NextDecade won approval from the US FERC to build the LNG terminal with up to five trains by November 2026.

After that, NextDecade secured a two-year extension from FERC in 2022.

Last month, Rio Grande LNG told FERC in its extension request that, given “intervening events”, substantial completion of Train 1 is not anticipated until the fourth quarter of 2027, and the four remaining Trains will be brought online sequentially thereafter, with Train 5 scheduled to be placed in service in the second quarter of 2031.

On April 30, 2026 the Commission issued public notice of the Rio Grande entities’ request for an extension of time, with interventions, comments, and protests due May 15, 2026.

FERC said in its decision on May 26 that no comments, interventions, or protests were filed.

“Based on the facts presented in the request and the case record, the Rio Grande entities are granted an extension of time until and including November 22, 2031 to complete construction of its Rio Grande LNG terminal and make it available for service,” the regulator said.

In July 2023, NextDecade took the final investment decision on the first three Rio Grande LNG trains.

In September and October last year, NextDecade made the final investment decisions on the fourth and fifth trains at its Rio Grande LNG facility.

This brings the total expected LNG production capacity under construction at Rio Grande LNG to approximately 30 mtpa.

NextDecade expects the facility to receive first gas by the end of this year and start shipping LNG produced at the first train in the first half of 2027.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.

LNG Canada offers option to First Nations to invest in Phase 2 storage tank

Shell-led LNG Canada has signed an agreement with five northwestern B.C. First Nations, giving them the option to invest up to C$1 billion ($711 million) to acquire an LNG storage tank slated for construction as part of the expansion of its Kitimat LNG export facility on the west coast of Canada.

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

Argent LNG awards marine and site engineering services contract to GIS

Argent LNG has awarded a marine, environmental, and site engineering services contract to Louisiana-based GIS Engineering in support of the federal permitting process for its proposed 25 mtpa LNG export terminal at Port Fourchon.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Adnoc’s XRG boosts stake in NextDecade’s Rio Grande LNG

Adnoc's investment unit XRG has completed the previously announced acquisition of an additional equity interest in Trains 4 and 5 of NextDecade's Rio Grande LNG terminal in Texas.

Cheniere’s Corpus Christi Stage 3 project 98 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 98 percent complete, as it continues to progress ahead of schedule, according to the latest construction update.