Power LNG expects to complete FEED this year

Texas-based Power LNG expects to complete front-end engineering and design (FEED) for its proposed Newport Galveston LNG facility in 2025.

The company said in its semi-annual progress report update filed with the US DOE on April 7 that (FEED) engineering is “on schedule, with FEL1 engineering currently in progress.”

According to Power LNG, the completion of the remaining FEED engineering is now projected for the end of the third quarter of 2025.

In addition, the air permitting process with the Texas Commission on Environmental Quality (TCEQ) is scheduled to begin in the third quarter of 2025, the firm said.

“We expect to reach a final investment decision (FID) by the end of Q4 2025,” Power LNG said.

ISO LNG tanks

Power LNG’s website does not provide many details regarding its project.

In April 2023, Power LNG secured authorization from DOE to export LNG from its proposed facility to be located on Galveston Island, Texas, to free trade agreement nations.

Power LNG requested long-term, multi-contract authorization to export domestically produced LNG in a volume equivalent to 7.0445 billion cubic feet per year (Bcf/yr) of natural gas for a term ending on December 31, 2050.

According to Power LNG, the facility is anticipated to “include a natural gas liquefaction plant with a production capacity of up to approximately 7.0445 bcf of LNG per annum at 100 percent capacity, a truck loading facility, a storage area, and dock access.”

Power aims to load the LNG supplies into ISO containers at the facility, then transport the containers by truck to a nearby loading dock within the facility, where it will be loaded onto ocean-going container vessels.

Additionally, Power LNG said, “the facility will be able to store up to 50 stacked ISO containers for a period of up to one week.”

Power said in the document that it had entered into a long-term lease agreement for the marine and industrial park with its management organization, GCC Supply & Trading.

The firm also said that it intends to enter into a long-term natural gas supply agreement with the Houston Pipeline (HPL) System, a subsidiary of Energy Transfer.

Power LNG said that it anticipates selling LNG to FTA countries in export markets in the Caribbean, Mexico, Central and South America.

Liquefaction solution

A progress report filed by Power LNG with DOE last year also shows that Power LNG made a decision to adopt Cryosys’ liquefaction technological solution.

“This solution was chosen for its exceptional efficiency, resulting in a substantial reduction of our build and implementation timeline. Notably, our LNG output has increased from 240,000 gallons per day to 380,000 gallons per day with minimal additional costs,” the firm said.

Power LNG also said in that report that it had achieved “significant milestones” in commercial negotiations, including the execution of a letter of intent (LOI) with PIC USA.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.
spot_img

More News Like This

US LNG exports down to 31 shipments

US liquefied natural gas (LNG) plants sent 31 cargoes during the week ending July 8, down five cargoes from the week before, according to the Energy Information Administration.

Ignitis books more regas capacity at Klaipeda FSRU

Lithuanian state-controlled energy company Ignitis has booked additional regasification capacities at the KN Energies-operated FSRU-based LNG import facility in Klaipeda, Lithuania.

Atlantic LNG shipping rates slightly up, Pacific rates down

Atlantic spot LNG shipping rates increased slightly this week, while Pacific rates dropped compared to the week before, according to Spark Commodities.

US LNG exports reach 36 shipments

US liquefied natural gas (LNG) plants sent 36 cargoes during the week ending July 1, up one cargo from the week before, according to the Energy Information Administration.