Sempra’s ECA LNG set to ship first export cargo

US LNG exporter Sempra is expected to soon ship the first export cargo from the first phase of its Energia Costa Azul LNG export terminal in Mexico, following the arrival of an LNG carrier at the 3.25 mtpa facility.

According to its AIS data provided by VesselsValue, the 2024-built 174,000-cbm Pacific Success was at the LNG facility on Tuesday morning. The vessel appears to be empty.

Kpler also reported on Monday that the TotalEnergies-operated Pacific Success was sailing in ballast in the northeast Pacific Ocean and is expected to arrive in the vicinity of the ECA LNG terminal later on Monday.

“The expected loading follows a sharp increase in feed gas deliveries into the terminal in June, signaling that commissioning had entered its final stages,” Kpler said.

LNG Prime invited Sempra to comment on the first ECA LNG export cargo.

Last month, Sempra Infrastructure, a unit of Sempra in which the latter is reducing its ownership to 25 percent, announced that ECA LNG Phase 1 liquefaction project in Ensenada started producing LNG as part of the commissioning process toward commercial operations.

According to the firm, ECA LNG Phase 1 is expected to reach substantial completion in the summer with sales under long-term sale and purchase agreements commencing shortly thereafter, when the facility begins commercial operations.

“With its strategic location on Mexico’s Pacific Coast, the ECA LNG facility will enable the supply of US natural gas to Asia and other Pacific Basin markets through the shortest shipping route, reducing transit times and transportation costs and providing customers with greater access to competitively priced US natural gas,” Sempra Infrastructure said.

A second phase is also under development at the same site.

Liquefaction capabilities added to ECA LNG regasification terminal

Sempra Infrastructure and France’s TotalEnergies added natural gas liquefaction capabilities to the existing ECA LNG regasification terminal, located north of Ensenada in Mexico’s Baja California.

The partners took FID on the development back in 2020, and ECA LNG Phase 1 includes a single-train liquefaction facility with a nameplate capacity of 3.25 mtpa of LNG.

Also, TotalEnergies and Mitsui & Co will offtake a combined 2.5 mtpa of LNG from the facility under 20-year deals.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.

LNG Canada offers option to First Nations to invest in Phase 2 storage tank

Shell-led LNG Canada has signed an agreement with five northwestern B.C. First Nations, giving them the option to invest up to C$1 billion ($711 million) to acquire an LNG storage tank slated for construction as part of the expansion of its Kitimat LNG export facility on the west coast of Canada.

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

Sempra Infrastructure’s ECA LNG exports first LNG cargo

US LNG exporter Sempra Infrastructure, a subsidiary of Sempra, said on Wednesday that the ECA LNG Phase 1 project in Ensenada, Mexico, has loaded and shipped its first cargo of liquefied natural gas (LNG).

TotalEnergies submits lowest bid in Pakistan LNG tender

A unit of French energy giant TotalEnergies has submitted the lowest bid in a tender to supply Pakistan with one spot LNG shipment this week.

Inpex buys 85 percent stake in Malaysian block from TotalEnergies

Japan's energy firm and LNG operator Inpex has acquired an 85 percent interest in Block 2E offshore Malaysia from French energy giant TotalEnergies.

CMA CGM, CCEC order LNG bunkering vessel in China

Greece's Capital Clean Energy Carriers (CCEC) and France's CMA CGM have ordered one LNG bunkering vessel from Chinese shipbuilder Nantong CIMC Sinopacific Offshore & Engineering. Upon delivery in 2028, the vessel will serve a long-term charter deal with a joint venture of TotalEnergies and CMA CGM.