PetroVietnam Power: first LNG power plant connected to grid

PetroVietnam Power's Nhon Trach 3 LNG power plant was connected to the national grid on February 5.

PV Power said in a statement that the plant generated 50 MW of electricity as part of its testing phase.

According to PetroVietnam’s unit, the LNG power plant is expected to start commercial operation in July this year, after meeting technical requirements.

Last week, PV Power said that the LNG power plant had completed the no-load operation test at 3000 rpm and was ready to be connected to the grid for the first time on February 1.

Earlier in January, PV Power fired up its Nhon Trach 3 LNG power plant.

In November 2021, PV Power broke ground on the Nhon Trach 3 and 4 plants in the southern province of Dong Nai, which are worth about $1.4 billion.

Vietnam’s first LNG power plants will have a total capacity of 1.5 GW.

South Korea’s Samsung C&T secured a contract from PV Power to build the plants in a consortium with Vietnamese contractor Lilama.

PV Power previously said the launch of these LNG plants had been delayed due to several issues, including those related to the project’s land lease and the power purchase agreement with Vietnam’s power utility EVN, which was signed in October last year.

By the end of January 2025, the total construction progress of Nhon Trach 3 and 4 projects had reached nearly 96 percent, according to the firm.

PV Power said it is working to accelerate the progress and put both plants into operation in 2025.

Deal with PV Gas

PV Power and PV Gas are still working to sign the final gas supply agreement for these plants.

The two firms are taking the final steps to sign the GSA, ensuring a long-term and stable gas source for future operations, PV Power said.

In November last year, PV Gas signed a contract with PV Power to supply the commissioning LNG cargo for the latter’s Nhon Trach 3 and Nhon Trach 4 power plants.

PV Gas launched its Thi Vai LNG terminal on October 29, 2023, after nearly 4 years of construction and commissioning.

This is Vietnam’s first LNG import terminal.

PV Gas is also working to increase the capacity of the facility to 3 mtpa-

Most Popular

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

PV Gas seeks spot LNG cargo

Petrovietnam Gas, a unit of state-owned Petrovietnam, has released a new tender inviting firms to submit bids for one spot LNG cargo for delivery to the Thi Vai LNG import terminal.

Shell, PV Gas seal LNG supply deal

Petrovietnam Gas, a unit of state-owned Petrovietnam, said it had signed a five-year deal to buy LNG from a unit of UK-based LNG giant Shell.

Petrovietnam, Nebula to strengthen LNG cooperation

State-owned Petrovietnam and US investment firm Nebula Energy are looking for ways to strengthen their cooperation in liquefied natural gas (LNG).

PetroVietnam Gas and EVN working to finalize supply deal for LNG power plants

PetroVietnam Gas, a unit of state-owned PetroVietnam, and compatriot power utility EVN are working to finalize an agreement to supply liquefied natural gas to EVN's Quang Trach II and III LNG power plants.