Nigeria’s UTM Offshore to award FLNG FEED next month, CEO says

UTM Offshore is expecting to award the front-end engineering and design (FEED) contract for Nigeria’s first floating LNG project in April, according to the company’s managing director and chief executive, Julius Rone.

Last year, Japan’s JGC completed the pre-FEED work for the FLNG. As a result of this design work, the FLNG’s capacity will be boosted by some 26 percent to 1.52 mtpa.

UTM Offshore also selected US-based KBR as the owner’s engineer to review JGC’s work and said that trader Vitol had joined the consortium to offtake the project’s LNG.

Rone told LNG Prime on Wednesday that UTM Offshore is working with JGC and KBR as well as South Korean shipbuilding giant Samsung Heavy Industries on the FEED contract.

“We are planning to sign the contract on or before April 15,” Rone said.

Nigeria’s UTM Offshore to award FLNG FEED next month, CEO says
Image: UTM Offshore

SHI and JGC have extensive FLNG experience. The two firms have previously delivered the second FLNG for Petronas and they are working together on the FEED for the third Petronas’ FLNG as well.

The duo also partnered with Technip Energies on the Coral FLNG, owned by Eni, which should go online this year.

Still targeting FID in 2022

UTM Offshore’s chief told LNG Prime in December that the company was planning to take a final investment decision on the floating LNG producer in the fourth quarter of 2022.

This followed the signing of a deal by Abuja-based UTM Offshore with the African Export-Import Bank (Afreximbank) to secure up to $5 billion for the development of the FLNG project.

Rone confirmed on Wednesday that the company is still targeting the FID in the last quarter of this year.

Nigeria’s UTM Offshore to award FLNG FEED next month, CEO says
Julius Rone (Image: UTM Offshore)

As per the FLNG, the unit would source gas from an existing platform located in the Yoho field, which lies in Oil Mining Lease 104, offshore Nigeria.

Also, the unit would process associated gas currently flared in order to cut carbon emissions and monetize additional reserves for the domestic and global market.

The Nigerian government holds a 60 percent interest in the Yoho crude oil joint venture, through NNPC, while ExxonMobil’s MPN holds the remaining 40 percent and operates the development that started production back in 2003.

UTM Offshore plans to launch the FLNG project in 2026.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

GTT bags Delfin FLNG gig

French LNG containment specialist GTT has secured a tank design order from South Korean shipbuilder Samsung Heavy for Delfin Midstream's 4.4 mtpa FLNG unit, which will be installed offshore Louisiana.

UTM inks gas supply deal for Nigerian FLNG project

Nigeria’s UTM Offshore has signed a long-term gas supply deal with a joint venture of Seplat and NNPC for its planned floating LNG project in Nigeria.

Modec clinches Coral Norte FLNG gig

Japan's Modec has secured a contract to supply an internal turret mooring system for the Eni-led Coral Norte (Coral North) FLNG project offshore Mozambique.

South Korea’s Samsung Heavy clinches another LNG carrier order

South Korean shipbuilding giant Samsung Heavy Industries has secured an order to build another liquefied natural gas (LNG) carrier for approximately $252 million.