Norway’s Equinor shuts Hammerfest LNG terminal

Norway’s Equinor has shut down its 4.3 mtpa Hammerfest LNG export plant due to a compressor failure.

Gassco data showed on Thursday that Hammerfest LNG will be offline until January 9, 2025.

LNG Prime invited Equinor to comment on the matter.

“After a safe Christmas with stable production, we had an issue yestreday on a compressor which re-injects CO2 to the field and it is therefore out of service,” a spokeswoman for Equinor said.

“We have decided to stop production today, January 2, at 16:00 for repair. The repair is expected to take a week, with a planned startup on January 9,” the spokeswoman said.

In April 2024, Equinor also closed the facility due to a gas leak.

The news comes just a day after Russia’s Gazprom halted pipeline gas supplies to Europe via Ukraine.

The Hammerfest LNG plant mainly supplies European countries with LNG. It liquefies natural gas coming from the Snohvit field in the Barents Sea.

Gas reaches Hammerfest LNG via a 160-kilometer gas pipeline which became operational in the autumn of 2007.

Equinor is the operator of both the Snohvit field and Hammerfest LNG with a 36.8 percent stake.

Other license owners of Snohvit are Petoro (30 percent), TotalEnergies EP Norge (18.4 percent), Neptune Energy Norge (12 percent), and Wintershall Dea Norge (2.81 percent).

The partners are currently working on upgrading the facility.

The Snohvit Future project will extend the productive life of Hammerfest LNG past 2030, and includes onshore compression and electrification of Hammerfest LNG.

Equinor and its partners said in December 2022 they would invest 13.2 billion Norwegian krone ($1.16 billion) to upgrade the facility.

In October 2024, Equinor reported an increase in costs for the Snohvit Future project.

Since the PDO (plan for development and operation) the cost increase is 1.9 billion 2024-NOK, Equinor said.

(Updated with a statement by Equinor.)

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.
spot_img

More News Like This

BP, Eni to send more gas to Angola LNG plant

Azule Energy, a joint venture of UK-based BP and Italy's Eni, and other partners will send more natural gas for liquefaction at the Angola LNG plant in Soyo following a final investment decision on the Greater PAJ project offshore Angola.

Gasum, Naftogaz book long-term capacity at Klaipeda FSRU

Finland's Gasum, Ukraine's Naftogaz, Lithuania’s Ignitis, Latvia’s Latvenergo, and Norway’s Equinor have booked long-term regasification capacities at the KN Energies-operated FSRU-based LNG import facility in Klaipeda, Lithuania.

Equinor kicks off Hammerfest LNG maintenance

Norwegian energy firm Equinor has shut down its Hammerfest liquefied natural gas (LNG) export plant for a planned three-day maintenance.

MISC, K Line charter another LNG-powered LCO2 carrier to Northern Lights

Malaysia's MISC and Japan's K Line have secured a second long-term time charter deal from Norway’s Northern Lights, a joint venture consisting of Equinor, Shell, and TotalEnergies, for an additional newbuild LNG-powered liquefied CO2 vessel.