Chevron pushes back Gorgon 2nd train restart

Chevron will need more time to place back online the second train at its Gorgon LNG plant in Australia after it found “weld quality issues” within the propane heat exchangers.

The second train has been offline since May 23 when it was closed as part of planned maintenance.

To remind, the Australian unit of the US energy giant said end-July it planned to restart the second unit at its 15.6 mtpa LNG facility on Barrow Island early this month.

But it said in a statement on Wednesday it would need additional time to complete the repairs. Chevron now expects to complete the repairs and to restart production next month.

“Following our ongoing technical work, we are further refining our approach and have decided some welds in targeted areas will require additional work,” it said.

Train 2 repair works to help with the remaining two trains

Last month, the Department of Mines, Industry Regulation and Safety also ordered Chevron to inspect the other two Gorgon trains allowing Chevron to shut them down in stages.

“We have discussed our plans with the regulator and will maintain alignment on its requirements for inspections and repairs on the Gorgon heat exchangers and the sequencing of work on Trains 1 and 3,” Chevron said.

Insights gained from the current repairs would contribute to more “efficient inspections and potential repairs” on the other two units.

The energy giant added it continues to provide LNG to customers under its contractual commitments. This also includes natural gas supplies to the Western Australian domestic market.

The Gorgon development is one of the world’s largest natural gas projects with a price tag of about $54 billion.

The plant liquefies gas coming from two offshore fields – Gorgon and Jansz-Io.

The first LNG cargo departed Barrow Island in March 2016 followed by gas supply to the domestic market in December.

Chevron Australia operates the project with a 47.3% share while ExxonMobil and Shell have a 25% stake, each.

Japan’s Osaka Gas, Tokyo Gas, and JERA own the remaining stakes in Gorgon.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.
spot_img

More News Like This

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.

MOL’s newbuild LNG carrier gets sails in South Korea

South Korea's Hanwha Ocean has completed the world’s first installation of the wind challenger system on an LNG carrier. The LNG carrier is owned by Japan's MOL and chartered by US energy giant Chevron.

Chevron resumes full Wheatstone LNG production after repairs

Chevron has resumed full production at the Wheatstone LNG facility near Onslow in Western Australia following the completion of repairs after Tropical Cyclone Narelle.

Chevron says Wheatstone LNG plant operating at 50 percent capacity

Chevron's Wheatstone LNG facility near Onslow in Western Australia is now operating at 50 percent capacity, while repairs continue on the second liquefaction train, a Chevron Australia spokesperson told LNG Prime on Thursday.