Chevron resumes full Wheatstone LNG production

Chevron’s unit in Australia has resumed full production at its 8.9 mtpa Wheatstone LNG terminal near Onslow after a fault reduced about 25 percent of the plant’s production.

“Chevron Australia confirms full production resumed last night (September 17) at the Wheatstone gas facility following a fault on September 14,” a Chevron spokesperson told LNG Prime on Monday.

“During this time LNG continued to be produced at approximately 80 percent of usual rates, and vessel loading continued. There has been no change to scheduled LNG deliveries,” the spokesperson said.

In addition, the spokesperson said that the Wheatstone domestic gas facilities were unaffected.

Industrial action

The news on September 14 of a fault linked to an instrumentation issue coincided with an announcement by the Offshore Alliance, which includes the Maritime Union of Australia and Australian Workers, of a complete stoppage of works at the Wheatstone and also the Gorgon facilities.

Workers at Chevron’s Gorgon and Wheatstone LNG plants have started protected industrial action on September 8 after talks between the energy giant and unions ended without an agreement.

Moreover, the Offshore Alliance, which includes the Maritime Union of Australia and Australian Workers’ Union, provided Chevron with a notice that work bans may apply for up to 24 hours a day from September 14.

The Offshore Alliance previously said in a social media post on that the “1411 turbine has tripped on the Wheatstone downstream facility and that all of this kicked in whilst the plant was being manned by Chevron’s “inexperienced” BCP workforce.

The Offshore Alliance said on Friday that “PIA has escalated today on the Chevron facilities and will continue to escalate over the coming days and weeks.”

Talks continuing

Chevron recently asked Australia’s Fair Work Commission to help resolve its ongoing dispute with unions representing its workers on both of the LNG projects.

The commission will hold its first hearing on September 22.

Chevron’s spokesperson said on Monday that there is no update regarding the action.

“Conciliation sessions are continuing today with the unions and Chevron,” the spokesperson said.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.
spot_img

More News Like This

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.

MOL’s newbuild LNG carrier gets sails in South Korea

South Korea's Hanwha Ocean has completed the world’s first installation of the wind challenger system on an LNG carrier. The LNG carrier is owned by Japan's MOL and chartered by US energy giant Chevron.

Chevron resumes full Wheatstone LNG production after repairs

Chevron has resumed full production at the Wheatstone LNG facility near Onslow in Western Australia following the completion of repairs after Tropical Cyclone Narelle.

Chevron says Wheatstone LNG plant operating at 50 percent capacity

Chevron's Wheatstone LNG facility near Onslow in Western Australia is now operating at 50 percent capacity, while repairs continue on the second liquefaction train, a Chevron Australia spokesperson told LNG Prime on Thursday.