Kinder Morgan restarts Elba Island LNG units after fire

U.S. energy company Kinder Morgan is restarting two of the three liquefaction units shut after a fire earlier this month at its Elba Island LNG export plant in Georgia.

The third train started the restart process late Tuesday and the first train will begin the process by the end of the week, Reuters reported on Thursday citing Kinder Morgan spokeswoman as saying.

The spokeswoman said that Kinder Morgan is conducting an investigation into the cause of the fire adding that the company doesn’t know when it will restart the second unit.

Kinder Morgan shut the second unit last week due to a fire in a mixed refrigerant compressor. This also prompted the company to close two adjacent units as a precaution.

Six of the ten liquefaction units at the LNG export plant, including the three shut by the fire, are available for service.

Kinder Morgan previously said it expects the other four to enter service by the end of the summer.

Elba, which shipped its first cargo in December 2019, will have a capacity of 2.5 million tonnes per year when all units enter service.

Kinder Morgan owns 51 percent of Elba while EIG Global Energy Partners holds a 49 percent stake.

The nearly $2 billion project has a 20-year contract with the Hague-based LNG giant Shell.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.
spot_img

More News Like This

Kinder Morgan seeks DOE extension for Gulf LNG export project

US energy company Kinder Morgan is seeking a non-FTA export extension from the US DOE for the planned Gulf LNG export terminal in Mississippi.

Kinder Morgan gets DOE OK to boost Elba Island LNG exports

US energy company Kinder Morgan has received approval from the US DOE to boost exports to non-FTA nations from the Elba Island LNG export plant in Georgia.

Kinder Morgan pursuing ‘substantial’ number of LNG opportunities

Rich Kinder, executive chairman of KMI said during the company's third-quarter earnings call on Wednesday that there are two...

Kinder Morgan to build $1.7 billion Texas LNG pipeline

Kinder Morgan CEO Kim Dang announced this in the company's fourth-quarter results report on Wednesday. Dang said the project is...