Santos CEO expects Papua LNG FID in early 2026

France's TotalEnergies and its partners plan to take a final investment decision on the Papua LNG export project in Papua New Guinea in the first quarter of 2026, according to Santos CEO Kevin Gallagher.

TotalEnergies has a 37.55 percent operating stake in the Papua LNG project, ExxonMobil has 37.04 percent, Santos owns a 22.83 percent interest, and JX Nippon holds 2.58 percent.

In April last year, the partners delayed the project’s FID to 2025, saying that they needed to keep working with contractors to obtain “commercially viable” EPC contracts.

“The Papua LNG project is making good progress towards an expected FID early in the new year,” Gallagher said during Santos’ first-half earnings call on Monday.

Last year, he said that FID is expected at the end of 2025.

During the earnings call on Monday, Gallagher also answered a question on what the critical paths are for achieving FID, and whether there are other factors beyond achieving acceptable EPC contracts.

He said that the operator “recycled some FEED activities.”

“At the time, which I think was late 2023 … costs were looking a bit higher,” he said.

“So we recycled some of that. And they’ve done a good job of taking considerable costs out,” Gallagher said.

“Again, we’ll update the market when we get to the point of making that decision. But we’re confident that project is heading in the right direction,” he said.

“And it should be in a position at least to be FID-ready around the end of this year,” Gallagher said.

Papua LNG

In March 2023, the Papua LNG partners launched fully-integrated front-end engineering and design (FEED) for the project, while TotalEnergies sold a small stake in the project to Japan’s JX Nippon Oil & Gas Exploration in June.

The project calls for the design of about 4 million tonnes per year of liquefaction capacity adjacent to the existing PNG LNG processing facilities, operated by ExxonMobil and located 20 kilometers northwest of Port Moresby, Papua New Guinea.

The facility will receive supplies from the Elk-Antelope gas field.

Also, the project includes the use of 2 million tonnes per year of liquefaction capacity in the existing trains of PNG LNG.

TotalEnergies CEO Patrick Pouyanne said earlier this year that “we are not desperate to make the project, but we are working hard to make it back on track, acceptable Capex to deliver some value.”

“We’ll have all the offers by September 2025, so we should be able to take decisions,” he said.

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.
spot_img

More News Like This

Sempra Infrastructure’s ECA LNG exports first LNG cargo

US LNG exporter Sempra Infrastructure, a subsidiary of Sempra, said on Wednesday that the ECA LNG Phase 1 project in Ensenada, Mexico, has loaded and shipped its first cargo of liquefied natural gas (LNG).

Sempra’s ECA LNG set to ship first export cargo

US LNG exporter Sempra is expected to soon ship the first export cargo from the first phase of its Energia Costa Azul LNG export terminal in Mexico, following the arrival of an LNG carrier at the 3.25 mtpa facility.

TotalEnergies submits lowest bid in Pakistan LNG tender

A unit of French energy giant TotalEnergies has submitted the lowest bid in a tender to supply Pakistan with one spot LNG shipment this week.

Inpex buys 85 percent stake in Malaysian block from TotalEnergies

Japan's energy firm and LNG operator Inpex has acquired an 85 percent interest in Block 2E offshore Malaysia from French energy giant TotalEnergies.