NextDecade gets FERC OK to boost Rio Grande LNG workforce

NextDecade's Rio Grande LNG has secured approval from the US FERC to increase the peak workforce to up to 7,500 per day at its LNG export terminal site in Texas.

FERC said on Friday it has granted Rio Grande LNG’s April 3 request to modify the workforce configuration and expand the construction work hours to include overnight and weekend work.

In addition, FERC confirmed the receipt of all federal authorizations relevant to Rio Grande LNG’s request, it said.

Rio Grande entities submitted a variance request to FERC to increase the peak workforce to 7,500 personnel (6,500 day shift, 1,000 night shift), up from the currently authorized 5,225 personnel.

Moreover, FERC also allowed construction to occur 24 hours a day, 7 days a week, with a limited set of construction activities occurring during nights and weekends, including but not limited to erecting structural steel, equipment installation, piping activities, welding, civil activities including concrete placement, trenching/excavation inside of the perimeter levee, and coating/fireproofing.

The company noted in its request that the Rio Grande entities are constructing all five trains simultaneously, requiring a greater overall workforce presence and multiple craft trades on site at the same time.

“As a result, the site will become physically constrained in the coming months unless the requested 24/7 work week is implemented and an increased number of peak workforce is authorized,” it said.

Matt Schatzman, NextDecade chairman and CEO, recently said that the company expects to start LNG production at the first train of its Rio Grande LNG terminal in the first half of 2027.

“With 30 million tonnes per annum (mtpa) of expected LNG production capacity under construction and the goal of doubling our capacity to 60 mtpa on site, growth at attractive returns continues to be a primary focus for the company,” Schatzman.

He noted that NextDecade initiated the pre-filing process with the Federal Energy Regulatory Commission (FERC) for Train 6 in November 2025.

The company expects to file a full application for Train 6 by mid-year, and “we expect to advance the development of Trains 7 and 8 throughout the year,” Schatzman said.

He said that NextDecade has been “in the market talking to potential customers for train six, and we’re seeing continued strong demand for incremental LNG supply in the 2030s and beyond.”

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

Argent LNG awards marine and site engineering services contract to GIS

Argent LNG has awarded a marine, environmental, and site engineering services contract to Louisiana-based GIS Engineering in support of the federal permitting process for its proposed 25 mtpa LNG export terminal at Port Fourchon.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Adnoc’s XRG boosts stake in NextDecade’s Rio Grande LNG

Adnoc's investment unit XRG has completed the previously announced acquisition of an additional equity interest in Trains 4 and 5 of NextDecade's Rio Grande LNG terminal in Texas.

Cheniere’s Corpus Christi Stage 3 project 98 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 98 percent complete, as it continues to progress ahead of schedule, according to the latest construction update.