US FERC issues final SEIS for NextDecade’s Rio Grande LNG project

The US Federal Energy Regulatory Commission (FERC) has released a final supplemental environmental impact statement for NextDecade's Rio Grande LNG facility and the accompanying pipeline in Texas. FERC continues to conclude that approval of the projects would result in "less than significant impacts."

FERC prepared the final supplemental environmental impact statement to address the August 6, 2024 opinion issued by the U.S. Court of Appeals for the District of Columbia Circuit regarding the Commission’s environmental review of the Rio Grande LNG terminal and Rio Bravo pipeline project.

In August 2024, the court issued an order vacating FERC’s remand authorization of NextDecade’s Rio Grande LNG facility and the pipeline, saying that FERC should have issued a supplemental EIS during its remand process.

In March, the court revised its August 2024 judgment against the Commission’s order for the first five liquefaction trains at the Rio Grande LNG facility.

After that, FERC released a draft supplemental environmental impact statement saying that it continues to conclude that approval of the project would result in “less than significant impact.”

Final SEIS conclusions

FERC said in its final SEIS on Thursday that project impacts on communities with environmental justice concerns would be “disproportionate and adverse because they would be predominately borne by the communities with environmental justice concerns identified and, specifically, communities in the areas near the Rio Grande LNG terminal may experience significant cumulative visual impacts.”

“Specific to air quality impacts, we clarify that the project’s air quality impacts on communities with environmental justice concerns would also be disproportionate and adverse,” the regulator said.

“However, RG LNG’s air quality analysis demonstrates that air quality impacts near the Rio Grande LNG terminal would not be significant, with the exception of two discrete areas just north of the LNG terminal where the cumulative model shows an exceedance of the annual PM2.5 SIL, and thus we conclude air quality impacts in those areas would be significant,” FERC said.

“Specific to the RB pipeline, the revised air quality dispersion modeling that shows that impacts from Compressor Station 1 would not exceed the NAAQS. Therefore, air quality impacts on communities with environmental justice concerns from operation of Compressor Station 1 would be less than significant,” it said.

“For all other resources, FERC staff continues to conclude that approval of the projects would result in less than significant impacts, with implementation of the environmental conditions set forth in the Commission’s prior authorizations for the project, and the additional mitigation measures recommended in the final supplemental EIS. Furthermore, staff does not recommend the CCS alternative,” the regulator said.

Rio Grande LNG

NextDecade is currently building three trains at the site located on the north shore of the Brownsville Ship Channel in south Texas.

In July 2023, NextDecade took the final investment decision on the first three Rio Grande LNG trains and completed a $18.4 billion project financing.

Phase 1, with a nameplate liquefaction capacity of 17.6 mtpa, has 16.2 mtpa of long-term binding LNG sale and purchase agreements.

Additionally, the firm closed a joint venture agreement for the first phase, which included approximately $5.9 billion in financial commitments from Global Infrastructure Partners (GIP), GIC, Mubadala, and TotalEnergies.

The deal also included options for the fourth and fifth trains.

NextDecade and compatriot Bechtel recently finalized EPC contracts worth $9.09 billion for the construction of the fourth and fifth trains and related infrastructure at the Rio Grande LNG facility.

In addition to these five trains, NextDecade announced plans in March to build up to five more trains at the Rio Grande LNG facility.

NextDecade said it is developing and beginning the permitting process for Trains 6 through 8.

The LNG terminal operator expects these trains to increase its total liquefaction capacity by approximately 18 mtpa once constructed and placed into operation.

Most Popular

Chevron pens Western Australian gas supply deal with Alinta

Chevron’s Australian unit has signed a new long-term deal with Alinta Energy to deliver domestic natural gas from its Gorgon and Wheatstone LNG projects and the Woodside-led NWS JV.
spot_img

More News Like This

Argent LNG awards marine and site engineering services contract to GIS

Argent LNG has awarded a marine, environmental, and site engineering services contract to Louisiana-based GIS Engineering in support of the federal permitting process for its proposed 25 mtpa LNG export terminal at Port Fourchon.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Adnoc’s XRG boosts stake in NextDecade’s Rio Grande LNG

Adnoc's investment unit XRG has completed the previously announced acquisition of an additional equity interest in Trains 4 and 5 of NextDecade's Rio Grande LNG terminal in Texas.

Cheniere’s Corpus Christi Stage 3 project 98 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 98 percent complete, as it continues to progress ahead of schedule, according to the latest construction update.